SUBJECT:Amendment No. 2 to Agreement No. 18-155 with NV5, Inc, ($109,022.36; revised not to exceed $3,794,115.22), for additional construction management services for the 24th Street Improvement Project.
STAFF RECOMMENDATION:

Staff recommends approval of the amendment.
BACKGROUND:

The 24th Street Improvement Project consists generally of expanding the 24th Street/Oak Street intersection to provide four lanes in both directions for 24th Street, and allowing for additional turn lanes for Oak Street. The Project also consists of widening 24th Street from four lanes to six lanes from Elm Street to C Street, and reconstructing and restriping the 23rd Street/24th Street one-way couplet roadway segments from D Street to 0.2 mile east of M Street to provide for four lanes in both directions.

 

Amendment No. 2 with NV5, Inc., is for additional construction management (CM) services including construction observation, biological monitoring, critical path model analysis, contract administration and project closeout. Throughout the construction of the project several design changes have occurred which in turn have extended the project duration. This, in turn, requires the extension of the CM services contract with NV5. Staff concurs with the increased amount and recommends approval of Amendment No. 2 to Agreement 18-155 for these services in the amount of $109,022.36.

 

Adequate local funds have been previously budgeted to cover these additional costs. There is no General Fund impact associated with these amendments.